|
|
|
CND // DECOMMISSIONING IN EUROPE / DECOMMISSIONING PROJECTS IN EUROPE / EWN Greifswald |
Decommissioning Projects in Europe The Greifswald Nuclear Power Plant (KGR)![]() ![]() The KGR is located 20 km in the north east of Greifswald. The Energiewerke Nord (EWN) are performing the world's largest decommissioning project, about eight (8) reactor units of the Russian pressurized water reactor "WWER-440" type. Short history
Site DescriptionOn the site of Greifswald, there are in total eight (8) reactor units of the Russian pressurized water reactor type "WWER-440". The units 1 to 4 are of the model V 230 and the units 5 to 8 of the more recent model V 213. The reactors are configured on a double-unit basis, i.e. two reactors are arranged in one reactor hall with certain mechanical equipment and secondary systems together. On the other hand, there is only one turbine hall (roughly 1 200 m long) for all reactors. There are also three plants for treatment and storage of liquid radioactive waste. The solid waste is stored in concrete pits. On site, there is furthermore a wet storage for fuel elements and a large warm workshop. On the smaller site in Rheinsberg, EWN is also decommissioning and dismantling a Russian prototype pressure water reactor "WWER-2". StrategyThe possibilities for an immediate dismantling of a safe enclosure have been investigated. The decision for an immediate dismantling was taken based on financial and radiological factors. The timely planning on the basis of a thorough technical and radiological registration of the plant and the organization of the overall waste management, covering the facilities for the treatment of residual material and waste as well as buffer and interim storage for the large amount of produced masses, are an absolutely necessary precondition for a successful project. Due to the limited reopening of the final disposal site in Morsieben (ERAM) and the lack of long term disposal possibilities in Germany, the Interim Storage North (ISN) on site as an independent integrated treatment and storage centre will be of central importance for the waste management scheme. The fuel elements will be loaded into "CASTOR" casks and transferred to the ISN for dry storage. LicensingThe licensing procedure is based on the conditions laid down in the decommissioning license issued 30 June 1995 (License for the decommissioning of the overall plant and for the dismantling of plant parts). The further dismantling of plant parts will be applied for step by step according to "§ 7 (3) of the Atomic Law". The scope and time schedule is determined by the proceeding of the overall project and its optimisation. So, the consistent use of personnel capacities, a continuous planning work and the continuity in the licensing procedures and in-process control can be guaranteed. According to the present project status, it can be distinguished between the following 7 license applications for the dismantling of plant parts:
Due to its relatively low activation, the reactor of unit 5 which was only in trial run will be transported in as large as possible parts (complete internals, reactor pressure vessel as a whole) to the ISN. It is assumed that a public hearing will only be required by the authorities for the application of the remote dismantling of the reactors 1-4. Project managementOn the basis of an analysis of the company development and personnel strategy, a technical concept was worked out and the project was broken down to working package level. The critical path goes over the mock-up remote dismantling in unit 5 to the remote dismantling in the units 1-4 and the dismantling of auxiliary systems and finally the building demolition.
Figure 1. Basic time schedule of the decommissioning project The project was optimized from the cost and personnel point of view in order to obtain a constant personnel number. For the project management, a software has been developed allowing in addition to the normal project control tasks to perform the technical planning, work preparation planning, tracking and control of dismantled material and radioactive waste etc ... Actual data from the dismantling operations are registered, evaluated and fed back into the system.
Figure 2. Project management Further information |
|||||
© 2001-2008 European Communities. All Rights Reserved. Disclaimer. |
|
||||